...
Click the Schedule tab and select the schedule (e.g. Account Transactions Scheduler 1498), which requires modifications.
Info Sigma enables you to modify the Starts On (start date and time) field. Once the Start On field is edited, the existing schedule gets updated with the updated date and time.
Make the necessary changes to the selected report schedule and click the Update option to update the modified report schedule.
A confirmation message appears.Click Ok.